4.12.B Action by the City Planning Commission

If the proposed Campus Development Plan is complete, complies with the base district regulations, and the proposed new construction is permitted by right or the new construction is authorized by Article 25, Section 25.3.G.4, then the Executive Director of the City Planning Commission shall sign of on the plan within 45 days of submittal of the completed plan.  The Executive Director may request further information from the applicant if necessary to determine compliance with the applicable regulations, specifying in detail the additional information required.  If such request for additional information is made, the running of the 45 day period to approve the plan is stayed until the applicant responds to the request.

Ord. No. 27,371, ยง2, April 28, 2017, Zoning Docket 125/16